‘Tejas’ LCA project likely to be completed in 2015

: Mar 19, 2013 - : 12:56 am

lca-tejas

The country’s indigenous Light Combat Aircraft (LCA) ‘Tejas’ programme is now expected to be completed only by March 2015 and is one of the major projects undertaken by the Defence Research Development Organisation(DRDO) which is running behind schedule by several years, the RajyaSabha was informed on Wednesday, March 14.

Union Defence Minister A K Antony said in a written reply that the deadline for the ‘Tejas’ project, which was originally scheduled for completion by December 2008, was likely to be extended till March 2015 as it had already breached the December 2012 revised deadline.

As for the DRDO’s delayed projects, the minister noted that the Naval LCA was now scheduled for completion by December 2014 as opposed to its original schedule of March 2010.

The Naval LCAs are likely to be the combat air element of the country’s first Indigenous Aircraft Carrier (IAC) that is now under construction at the Cochin Shipyard (CSL) and which in all likelihood may join the Navy by December 2015.

MORE NEWS

Headquartered in Singapore with reporters spread across all major regions, GBP Aerospace & Defence is a leading media house that publishes three publications that serve the aerospace and defence sector - Asian Defence Technology, Asian Airlines & Aerospace and Daily News. Known industry-wide for quality journalism, GBP Aerospace & Defence is present at more international tradeshows and exhibitions than any other competing publication in the region.
For over three decades, our award-winning team of reporters has been producing top-notch content to help readers stay abreast of the latest developements in the field of commercial aviation, MRO, defence, and Space.

Popular Posts

Copyright 2024. GBP. All Rights Reserved.

Home Defence & Security Space Commercial Aviation Maintence Repair & Overhaul Daily News Events About Us

×