       SCHIEBEL EMBARKS ON



        AUSTRALIAN NAVAL JOURNEY



        Last year, the Royal Australian Navy (RAN)   two years of acquisition, and five years  Australia (Aerosonde V4/HQ).
        selected Schiebel’s S-100 Camcopter rota-  of sustainment. Knechtl said no decision
        ry-winged  UAV  as  its  next  platform  for   has been made on the number of aircraft  Sea 129 Phase 5 will span 30 years, with
        shipboard use. Raytheon Australia is head-  to be procured. Instead, the RAN talks  five-year  rolling  block  upgrades  occur-
        ing the programme, and it was appointed to   about eight capability bricks, with Schiebel  ring to incorporate new technologies.
        meet the single-source acquisition, rather   Pacific expecting each brick to consist of  Commencing in 2024, Block 1 will acquire
        than the navy proceeding through a com-  2-3 aircraft. A handful more UAVs would be  eight capability bricks of UAVs operating
        petitive tender.                       needed for training purposes.          primarily from Arafura-class offshore patrol
                                                                                      vessels and Anzac-class frigates.
        This programme is known as Project Sea   The RAN’s 822x Squadron has already been
        129 Phase 5 Block 1, and many were     operating three S-100s since 2018, so the  Block 2 will proceed from 2029, refreshing
        somewhat surprised that Australia was   navy is familiar with the platform, and this  Block 1 systems and adding five further
        fast-tracking the procurement in this way.   past experience could have been upper-  capability bricks to equip Hunter-class frig-
        Canberra calls it ‘progressive industry   most in the RAN’s mind. Indeed, the trio  ates and deployment on other ship classes.
        engagement’, and the aim is to get S-100s   was retrofitted with heavy-fuel S-2 engines.  There will also be Block 3, introducing a
        in the hands of the navy more quickly,   That particular contract was extended in  comprehensive update and refresh of
        reaching an initial operational capability   July 2021 for a further three years, and  the UAV to integrate new payloads and
        a whole 18 months earlier by the RAN’s   three extra S-100s were added to the navy’s  capabilities.
        reckoning.                             squadron.
                                                                                      Incidentally, Schiebel announced its new
        However, the Defence Strategic Review   The design,  development,  manufacture,  and larger S-300 Camcopter at last week’s
        has created uncertainty for a number of   integration and support of the system will  IDEX 2023 exhibition in Abu Dhabi. The
        defence projects, and the same is true of   be undertaken in Australia, at Schiebel’s  S-300 offers extended range, greater endur-
        Sea 129 Phase 5. With the acquisition cur-  hub in Shoalhaven, New South Wales. It will  ance and a larger 250kg payload capacity. It
        rently in somewhat of a holding pattern,   create approximately 100 jobs in Australia.  could thus carry other types of radars or be
        Fabian Knechtl, Schiebel Pacific’s Managing                                   used for submarine warfare, for instance.
        Director, nevertheless hopes a contract will   Schiebel defeated other contenders BAE
        be signed before the end of 2023.      Systems Australia, Insitu Pacific (with the  Knechtl said that the S-300 could be
                                               ScanEagle/Integrator), Northrop Grumman  offered to Australia too as part of future
        Once signed, it is expected to comprise   Australia (AWHero) and Textron Systems  blocks and upgrades.